According to SAED public relations, at 01:30 am on March 13th of this year (2017), The oil is extracted from Azar oil wells, reached the Dehloran facilities.
The oil is extracted from Azar wells 3, 7, 9 and 13, were sent to Modified Early Production System (MEPS) over 14 km flow lines, after primary activities and injection of chemical required by wellhead equipment.
MEPS transferred the oil to the pipeline by oil pumps after the gas separation and processing.
It should be noted, that pigging operation of 130 km lines of Azar filed to Dehloran facilities and then desalination unit took placed in 6 days.
The first PIG was launched from central processing unit on 0 km to tee junction on 121 km and the second PIG was sent on 121 km and successfully was received on 129 km.