Vital progresses in commissioning works for the significant electrical and control fronts were made in Wednesday of the ongoing week.
Subsequent to completion of the executive operations, and pre-commissioning & commissioning tests, the main electrical substation of the oilfield was established and both transformers of the 132-to-11 substation have been successfully put in service.
Within the same day, the main LV generators of the early production process unit have been put in service. Then the control room of the early production processing unit was also brought into the circuit successfully, once power at the processing LV substation was normalized.
It is noteworthy that operation of this oilfield in the early March of this year, with a production of 1500 barrels of oil in the early production phase, will bring the great news of success in this Iranian most complicated oilfield.